NAP Location: Health Center Site, 123 Main Street, City, State, Zip Code
Total NAP minor A/R funding request: $250,000
Total funding from other sources: $15,000
Total Project Cost: $265,000
For our minor A/R project, we propose converting an existing large meeting room into five new exam rooms and one office and removing a wall to expand laboratory space. It also will include new tile flooring in the exam rooms and medical records room, and new carpet in the reception area, conference room, waiting room, and provider offices. We will install more energy efficient lighting and repaint throughout the 5,500 SF space.
In addition, we will purchase clinical and non-clinical equipment. We expect to begin renovation within 60 days of obtaining all local approvals. We expect to complete the work no more than 3 months after it begins.
Sample minor A/R budget justification
Line Item | Allowable Costs | Unallowable Costs |
---|---|---|
Line 1 - Administrative and legal expenses | $10,000 for evaluation of environmental impact and to pay staff costs directly related to this project. | |
Line 2 - Land, structures, right-of-way, appraisals | ||
Line 3 - Relocation expenses and payments | $1,500 for storing furniture and equipment during renovation. | Moving clinic equipment and furniture to the new location upon project completion at a total cost of $2,500. |
Line 4 - Architectural and engineering fees | $8,500 for architectural and engineering fees, which will cover the following: mechanical and electrical design, bid construction documents (plans and specifications), and assistance during the construction bidding (answer questions presented by the contractors). | |
Line 5 - Other architectural and engineering fees | ||
Line 6 - Project inspection fees | $7,500 for project inspection fees. The inspections will be conducted in accordance with the local Department of Public Works standard and building codes. | |
Line 7 - Site work | $3,500 to purchase and install a sign on the outside wall of the building. | |
Line 8 - Demolition and removal | $24,000 for removal and disposal of interior partitions and materials in the interior of the existing building. | $8,500 for removal and proper disposal of existing asbestos floor tile. |
Line 9 - Alteration and renovation |
$85,000 to renovate 5,500 square feet of existing space. This renovation cost is derived from the following cost breakdown: structural ($9,000), architectural ($40,500), mechanical ($14,500), and electrical ($21,500). The structural cost of $9,000 is comprised of the following: re-building two outdoor accessibility ramps, concrete column footing, and first floor walls. The architectural cost of $40,500 includes the following: concrete work, masonry glass units, metals (aluminum railings, handrails), woods and plastic (cabinets and casework shelving, table counter tops), doors and windows (metal windows, aluminum doors and frames, high moisture frames, wood doors, door hardware, exterior window shutters, pass and observation window, glazing-laminate exterior),; and finishes (ceiling suspension, gypsum board (wall partitions) on metal framing, ceramic tiles, plaster on CMU, acoustical ceiling, resilient flooring, resilient wall base and accessories, painting). The mechanical cost of $14,500 includes the following: water, sewer, and piping systems (plumbing fixtures and equipment - water closet, sinks, electric water heater, funnel drain), cold water, hot water, water storage tank, and piping insulation, oxygen piping lines and accessories; fire protection system (fire sprinkler system - steel piping, sprinkler heads, steel hose, inspector test valve), installation of four new air conditioning units. The electrical cost of $21,500 includes the following: lighting system (PVC conduit, EMT conduit, lighting fixtures and wiring, light switches and lighting control, wall outlets wiring), communication system (PVC conduit, EMT, computer data networking system (outlet, conduit and CAT 5E cabling), telephone outlet, CA TV outlet, PA intercom system (conduit and wiring), security alarm conduit system), and fire sprinkler system (fire alarm cable, fire alarm heat detector, fire alarm control panel). |
|
Line 10 - Equipment |
$104,000 for loose, movable equipment items. See itemized equipment list for additional information. |
|
Line 11 - Miscellaneous | $4,000 for artwork for the waiting room and pediatric exam rooms. | |
Line 12 - SUBTOTAL |
$244,500 |
|
Line 13 - Contingencies | $5,500, which is less than 5% of lines 7, 8, and 9. | |
Line 14 - SUBTOTAL |
$250,000 |
$15,000 |
Line 15 - TOTAL PROJECT COSTS |
$265,000 (Sum of allowable and unallowable costs from Line 14 - SUBTOTAL) |
|
Line 16 - NAP one-time funds |
$250,000 |
Sample allowable and unallowable costs
The following table lists sample allowable and unallowable costs for a proposed minor A/R project.
The total federal and non-federal cost of your minor A/R project must be less than $1,000,000, excluding the cost of moveable equipment.
Refer to the cost principles in 45 CFR Part 75 for details on allowable costs.
Fixed equipment includes items that require you to modify the facility for its installation or removal. Include them in the construction contract: for example, HVAC units, ductwork, generators, fume hoods, sinks, fixed shelving, built-in sterilizers, built-in refrigerators, and wiring or cabling inside walls or above ceilings.
Cost Categories | Allowable Costs | Unallowable Costs |
---|---|---|
Administrative and legal expenses |
|
|
Relocation |
|
|
Architectural and engineering fees |
|
|
Project inspection fees | Clerk-of-the-works, inspection fees, structural certification, etc., to be provided by architectural engineering firm or applicant’s staff | Fees not directly related to the project |
Site work | Minor alteration at entrances and adjacent sidewalks as required for ADA compliance |
|
Demolition and removal | Costs of demolition or removal of structures for improvements such as wall finishings and fixtures (reduce the costs on this line by the amount of expected proceeds from the sale of salvage) |
|
Alteration and renovation |
|
|
Equipment |
|
|
Contingencies |
|
Contingency costs above the allowable percentage |